PGCIL debuts in intrastate power transmission

PGCIL debuts in intrastate power transmission

Earlier this month, Power Grid Corporation of India (PGCIL) debuted in the intrastate power transmission space by winning a concession in Uttar Pradesh, under the tariff-based competitive bidding route. The Central utility clinched the transmission scheme associated with the upcoming 2×660-mw Jawaharpur power generation project in Uttar Pradesh.

For PGCIL, which specializes in interregional and even cross-border transmission lines, winning an intrastate project assumes significance. When the TBCB mechanism was launched in January 2011, the initial projects were all of interregional lines—crucial components of the National Grid. It is only in recent years that state governments started using the TBCB mechanism for intrastate lines. However, this culture did not spread widely with only few states like Uttar Pradesh, Haryana, Rajasthan and a few others, deciding to adopt this modality.

Coming back to the concession won by PGCIL, the project special purpose vehicle is “Jawaharpur Firozabad Transmission Ltd,” which was incorporated on August 20, 2018, as a wholly-owned subsidiary of REC Transmission Projects Company Ltd. This SPV has now been transferred to PGCILwho will develop the project on build, own, operate, maintain (BOOM) basis under a 35-year concession period.

The transmission scheme comprises of three broad elements:

  • LILO of the 765kV Mainpur-Greater Noida single-circuit line at Jawaharpur thermal power project
  • 400kV double-circuit quad line from Jawaharpur thermal power project to Firozabad
  • 400/220/132kV air insulated substation (AIS) substation at Firozabad

 

The project will also include some more LILOs and a 132kV double-circuit line connecting the upcoming Firozabad substation to Narkhi.

UP takes the lead: It is worth observing that Uttar Pradesh has formalized three intrastate power transmission projects this year. This is a very commendable achievement considering that there was hardly any movement in other states in the intrastate TBCB power transmission space.

Of the three projects that UP formalized this year, one project (the Jawaharpur scheme discussed above) has gone to PGCIL and two have been bagged by Adani Power. In June this year, Adani Transmission Ltd (ATL) clinched the Ghatampur power transmission project under the tariff-based competitive bidding route, marking its first presence in Uttar Pradesh.

The transmission project involves around 900 ckm of transmission lines at 765kV and 400kV levels. Some major 765kV lines include Ghatampur-Agra, Agra-Greater Noida and Ghatampur-Hapur.

Incidentally, the Ghatampur project saw very aggressive bidding at the RfP stage with PGCIL being the only other contender in the race when the project ultimately went to Adani Group.

Very recently, Adani won the transmission scheme involving evacuation infrastructure for the upcoming 2×660-mw Obra-C thermal power project of state government utility Uttar Pradesh Vidyut Utpadan Nigam Ltd (UPVUNL).

Uttar Pradesh is seen to be very aggressive in recent years, in all aspects of the power value chain—generation, transmission and distribution. The northern state is gearing up to meet growing demand from both the industrial and household sector. Under the nationwide household electrification scheme “Saubhagya”, over 68 lakh households have been electrified since October 2017. This represents nearly 30 per cent of the 231 lakh households that have been electrified since the launch of Saubhagya.

UP is doing well to expedite its power generation projects and also step up household electrification. Its effort in accelerating the creating of power transmission infrastructure is a step in the right direction.

The author of this article, Venugopal Pillai, is Editor, T&D India, may be reached on venugopal.pillai@tndindia.com. The views expressed here are personal. 

Leave a Reply

Your email address will not be published. Required fields are marked *